Loft conversion interior London
Loft Conversions 24 February 2026 6 min read

How Long Does a Loft Conversion Take? A Week-by-Week Timeline

Quick Answer

A dormer loft conversion takes 8–12 weeks on site. A Velux conversion can be done in 6–8 weeks. A mansard conversion takes 12–16 weeks. Add 4–8 weeks for pre-construction (structural drawings, Building Regulations, Party Wall notices) and the total programme from instruction to completion is typically 16–24 weeks.

A dormer loft conversion typically takes 8–12 weeks from start to finish. But that figure hides a lot of variation. The type of conversion, the structural condition of your roof, and whether you need planning permission all affect the programme significantly. What follows is a realistic week-by-week breakdown of what happens and when.

Duration by Conversion Type

Conversion TypeTypical Duration (on site)Notes
Velux / Roof Light6–8 weeksNo structural changes to roof shape. Fastest option.
Dormer (rear)8–12 weeksMost common in London terraces. Requires structural work.
Hip-to-Gable10–14 weeksRequires rebuilding one or both hip ends. More complex.
Mansard12–16 weeksSignificant structural alteration. Usually requires planning.
L-Shaped Dormer10–14 weeksTwo dormers joined. Common on Victorian terraces.

Week-by-Week: A Typical Dormer Loft Conversion

Pre-ConstructionWeeks 1–4
Week 1–2Structural engineer survey and calculations
Week 2–3Architectural drawings prepared and submitted for Building Regulations
Week 3–4Party Wall notices served (if applicable — 2-month minimum notice period)
Structural WorkWeeks 5–7
Week 5Scaffolding erected, roof tiles stripped in working area
Week 5–6Steel beams installed (RSJs or UC sections per engineer's spec)
Week 6–7New floor joists, dormer frame or mansard structure built
WeathertightWeeks 7–9
Week 7–8Roof covering reinstated — new tiles, flat roof membrane, or zinc/lead
Week 8Dormer cheeks clad (render, tile hanging, or zinc)
Week 8–9Velux or dormer windows installed and made weathertight
First FixWeeks 9–11
Week 9–10Staircase installed (new loft stair or reconfigured existing)
Week 9–11First fix electrics — cables run, consumer unit upgraded if needed
Week 10–11First fix plumbing if en-suite planned — soil stack extended
Second Fix & FinishingWeeks 11–14
Week 11–12Plasterboard, insulation, and skim coat
Week 12–13Second fix electrics — sockets, lighting, smoke detectors
Week 12–13Second fix plumbing — sanitaryware, shower enclosure
Week 13–14Joinery — skirting, architraves, doors, built-in storage
Week 14Decoration, flooring, snagging, and Building Control final inspection

What Slows a Loft Conversion Down

Party Wall disputes are the single most common cause of programme delays. If a neighbour dissents, the appointment of a Party Wall surveyor and agreement of an Award adds 4–8 weeks before work can start. Serve notices as early as possible — ideally the day you receive your Building Regulations approval.

Structural surprises are the second most common cause. Older London properties sometimes have undersized or damaged ceiling joists that require additional steel before the loft floor can be formed. A pre-contract structural survey identifies these issues before they become programme problems.

Building Control inspection delays can also add time if the inspector is not booked in advance. Your builder should be booking inspections at least a week ahead of each stage. If they are not, ask why.

Ready to Start Your Loft Conversion?

TCM manages the entire process — from structural engineer to Building Control sign-off. Get a fixed-price quote today.